SESB to repair Ranau transmission towers
The main structure of an affected tower.
Kota Kinabalu: Sabah Electricity Sdn Bhd (SESB) is carrying out emergency repairs to two transmission towers in Ranau affected by active ground movement.

SESB Chief Executive Officer, Ir Ts Mohd Yaakob Hj Jaafar, said on-site inspections found the stability of 275kV transmission line tower sites compromised.

The condition of the two towers is critical for the 275kV Kolopis-Segaliud Grid transmission line.

“200MW needs to be channelled to the East and West coast of Sabah every day.

“SESB has taken swift action to install a temporary diversion tower, the Emergency Restoration System (ERS) at the site in collaboration with Tenaga Nasional Berhad (TNB) and the State Government.

“Eight ERS towers will be installed in these two locations to ensure that the energy supply to the East Coast of Sabah is unaffected,” he said on Friday.

He said removal works began on Feb 7, and is expected to be completed within five weeks.

 

* Follow us on Instagram and join our Telegram and/or WhatsApp channel(s) for the latest news you don't want to miss.

* Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available.





ADVERTISEMENT






Top Stories Today

Sabah Top Stories


Follow Us  



Follow us on             

Daily Express TV  







close
Try 1 month for RM 18.00
Already a subscriber? Login here
open

Try 1 month for RM 18.00

Already a subscriber? Login here