Pan Borneo Highway: Sarawak’s phase one to be fully opened in second quarter of year
Published on: Tuesday, April 09, 2024
Published on: Tue, Apr 09, 2024
By: Bernama
Text Size:
Share this story
Pan Borneo Highway: Sarawak’s phase one to be fully opened in second quarter of year
For illustrative purposes only.
KUCHING: Phase one of the Sarawak Pan Borneo Highway (LPB) project will be fully opened in the second quarter of this year, said Works Minister Datuk Seri Alexander Nanta Linggi.

He said that, so far, the work progress of the project has reached 99 per cent.

Advertisement
“Phase one of the Sarawak LPB is expected to be fully opened in the second quarter of this year, except for the Lambir section (under work package 11) in Miri, which needs to be redesigned and it is expected to be ready in 2026,” he said in a statement today.

Phase one of the Sarawak LPB construction involves a total distance of 706 kilometres (km) from Telok Melano to Miri.

SPONSORED CONTENT
Enjoy a taste of Malaysia, everyday with Ayam Brand™  local pastes
Enjoy a taste of Malaysia, everyday with Ayam Brand™ local pastes
SHAH ALAM: Fact: Every time Malaysians travel abroad, we almost immediately miss the taste of home. You don’t need to be homesick to celebrate Malaysia’s rich culinary heritage when you can savor the authentic taste of Malaysia in your own home with Ayam Brand™  cooking pastes.
Meanwhile, Nanta said a meeting was held between his ministry and the Sarawak Public Works Department (JKR) yesterday, which discussed issues related to the maintenance of state and federal roads in Sarawak, especially involving the redline alignment.

He said the term redline refers to the existing original routes built before the construction of the LPB.

Advertisement
“In Sarawak, the redline alignment involves the areas of Kuching, Serian, Sibu, Bintulu, Julau and Miri. The standard of these redline routes, built previously, differs from the LPB and the quality of these redline routes needs to be upgraded.

“Phase one of the Sarawak LPB involves a distance of 786km, but there are road alignments of 136.7km that were not included in the LPB's construction and are now in poor condition. Several solution models were proposed at the meeting, and all these proposals will be studied in detail,” he said.
* Follow us on Instagram and join our Telegram and/or WhatsApp channel(s) for the latest news you don't want to miss.

* Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available.
Advertisement
Share this story
Advertisement
Advertisement
Follow Us  
Follow us              
Daily Express TV  
© Copyright 2024 Sabah Publishing House Sdn. Bhd. (Co. No. 35782-P)
close
Try 1 month for RM 18.00
Already a subscriber? Login here
Try 1 month for RM 18.00
open
Try 1 month for RM 18.00
Already a subscriber? Login here