“Meanwhile, for the taxiway section, the remaining work is completion of the paving works, including the markings and remaining installation work for the aeronautical lighting system,” the statement said. The project, implemented under the 11th Malaysia Plan, with the project scope involving extension of the runway from 2,133 metres to 2,500 metres, construction of a new connecting taxiway, widening of the aircraft parking areas and upgrading of the flight navigation equipment.