Federal Government pays RM1.2bn in land compensation for Sabah Pan Borneo Phase 1
For illustrative purposes only.
Kuala Lumpur: A total of RM1.2 billion has been paid by the federal government for land compensation for the Sabah Pan Borneo Highway (PBH) Phase 1 Project so far, said Deputy Minister of Works Datuk Seri Ahmad Maslan.

He said for the Sarawak PBH, the total land compensation payment made was RM737 million.

Advertisement
“The government is bearing the entire cost of compensation, losses and administrative costs to ensure that landowners do not suffer losses,” he said.

He was replying a question by Isnaraissah Munirah Majilis (Warisan-Kota Belud) on the justification for the surge in the cost of the Sabah PBH Phase 1 Project which has now reached RM24.889 billion compared to the initial estimate in 2015 and the amount of land compensation during an oral question and answer session in the Dewan Rakyat, on Tuesday.

SPONSORED CONTENT
The 2026 D-MAX also introduces an 8-speed automatic gearbox with sequential shift across the range, including the Single Cab variant, making it the first pick-up truck in Malaysia to offer an automatic transmission in that body style.
Ahmad said the increase in cost from the initial estimate of RM12.86 billion in 2015 to RM24.889 billion at present was due to the project switching to the Federal Conventional Contractor method following the termination of the Project Delivery Partner (PDP) model in 2019.

According to him, the termination of the PDP model due to national interest factors required a reassessment of the remaining work and scope of the project after five years from the original assessment period.

Advertisement
“From a technical point of view, the increase in the cost of this project was due, among other things, to factors such as changes in scope and design, geotechnical structures and soil treatment as well as large-scale utility relocation works,” he said.

He said the cost of Phase 1A involved 16 work packages with a total cost of RM10.9 billion while Phase 1B involved 19 work packages with a total cost of RM13.989 billion.

Advertisement
Ahmad said that apart from technical factors, the increase in costs was also influenced by inflation and the increase in the price of major domestic and global construction materials such as iron, bitumen and cement, in addition to the increase in machinery costs and labour costs.
* Follow us on our official WhatsApp channel and Telegram for breaking news alerts and key updates!

* Do you have access to the Daily Express e-paper and online exclusive news? Check out subscription plans available.
Advertisement
Share this story
Advertisement
Advertisement
Follow Us  
           
Daily Express News  
© Copyright 2026 Sabah Publishing House Sdn. Bhd. (Co. No. 35782-P)
close
Try 1 month for RM 18.00
Already a subscriber? Login here
Try 1 month for RM 18.00
open
Try 1 month for RM 18.00
Already a subscriber? Login here